Austin Permit Report: September 2026, Urban Infill
The Cedar Market Monitor is a monthly newsletter for the people building Austin's housing. We use public permit data to show where the market is heading: where new homes are going, how long approvals take, and who's building. This issue covers September 2026, with data
through 5 November 2026.
Last 3 months+23%422 permits Jul–Sep 2026, vs 344 a year earlier
Permit Issue time63 daysmedian SF, last 12 months
In the pipeline10,179permitted since Jan 2025, not yet finished
What got permitted
Detached houses carried 106 of September’s 116 infill homes.
Over twelve months infill homes are down 7%, and the missing middle was 18% of them, down from 26% the year before. Homes, not permits.
Pipeline
10,179 homes permitted since January 2025 haven’t been finished yet.
That’s the supply still coming: 84% of the
12,167 homes permitted in that time. 79% are in
apartment buildings (5+ homes), and five ZIPs hold
47% of them, led by 78702 (1,640) and 78758 (1,427). Most permits get built: 94% of homes permitted 2016–22 were finished.
Teardowns
Five ZIP codes had 64% of Austin’s 434 home teardowns in the last twelve months.
ZIP
Oct 2025 – Sep 2026
Year before
1. 78704
65
73
2. 78757
61
71
3. 78702
53
51
4. 78703
50
52
5. 78745
47
56
Private whole-house demolitions inside the City of Austin full-purpose limits, one per lot per year:
23 ZIPs in all (460 teardowns Oct 2024 – Sep 2025).
Permit issue time
A single-family permit takes a median 63 days to issue.
Building type
Permits
Median days
Excl. slowest 10%
Single-family
1,399
63
56
2–4 units
190
118
103
Multifamily & mixed use*
113
746
483
Median days from application to issue, permits issued Oct 2025 –
Sep 2026. The last column removes the slowest 10% to account for stalled
applications. *44% of multifamily & mixed use permits were applied for more than three years earlier, so that figure mostly reflects a backlog clearing.
Where
Five ZIP codes carried 66% of September’s infill homes.
None1–45–910–1920+
ZIP
Homes
Share
1. 78702
23
20%
2. 78747
23
20%
3. 78754
12
10%
4. 78745
10
9%
5. 78704
8
7%
Fastest riser: 78754, from 0 to 55 infill homes in Jul–Sep 2026 against a year earlier. Only permits inside the City of Austin full-purpose limits are counted, so ZIPs that straddle the city line
show the city’s part only.
Who’s building
Milestone Community Builders, LLC led with 84 homes in the last six months.
Builder
Homes
Permits
Milestone Community Builders, LLC
84
78
Century Land Holdings II, LLC
68
68
New Home Co
44
44
Trophy Signature Homes
43
43
David Weekley Homes
29
29
Infill homes permitted April – September 2026, out of
901. The permit holder is usually the general contractor rather than the
developer, and one firm can appear under several names. 104 homes on 103 permits (12%) name no holder and are not ranked.