Austin Permit Report: October 2026, Urban Infill

The Cedar Market Monitor is a monthly newsletter for the people building Austin's housing. We use public permit data to show where the market is heading: where new homes are going, how long approvals take, and who's building. This issue covers October 2026, with data through 6 November 2026.

Permit snapshot

Permits issued177 vs 91 in Oct 2025 · 188 homes
Last 3 months+47% 424 permits Aug–Oct 2026, vs 288 a year earlier
Permit Issue time60 days median SF, last 12 months
In the pipeline11,098permitted since Jan 2025, not yet finished

What got permitted

Detached houses carried 140 of October’s 188 infill homes.

Detached house140Attached single-family9Duplex193–4 unit buildings19Accessory unit1

Over twelve months infill homes are up 2%, and the missing middle was 19% of them, down from 24% the year before. Homes, not permits.

Pipeline

11,098 homes permitted since January 2025 haven’t been finished yet.

5+ unit buildings8,809Single homes2,0292–4 unit buildings260

That’s the supply still coming: 85% of the 13,086 homes permitted in that time. 79% are in apartment buildings (5+ homes), and five ZIPs hold 49% of them, led by 78702 (1,643) and 78758 (1,427). Most permits get built: 94% of homes permitted 2016–22 were finished.

Teardowns

Five ZIP codes had 64% of Austin’s 452 home teardowns in the last twelve months.

ZIPNov 2025 – Oct 2026Year before
1. 787047174
2. 787576372
3. 787035647
4. 787025247
5. 787454659

Private whole-house demolitions inside the City of Austin full-purpose limits, one per lot per year: 23 ZIPs in all (460 teardowns Nov 2024 – Oct 2025).

Permit issue time

A single-family permit takes a median 60 days to issue.

Building typePermitsMedian days Excl. slowest 10%
Single-family1,4656053
2–4 units209128112
Multifamily & mixed use*107482482

Median days from application to issue, permits issued Nov 2025 – Oct 2026. The last column removes the slowest 10% to account for stalled applications. *36% of multifamily & mixed use permits were applied for more than three years earlier, so that figure mostly reflects a backlog clearing.

Where

Five ZIP codes carried 47% of October’s infill homes.

78617: 11 homes in October 202678653: 1 home in October 202678660: 0 homes in October 202678701: 0 homes in October 202678702: 3 homes in October 202678703: 8 homes in October 202678704: 21 homes in October 202678705: 3 homes in October 202678717: 0 homes in October 202678721: 2 homes in October 202678722: 9 homes in October 202678723: 6 homes in October 202678724: 0 homes in October 202678725: 0 homes in October 202678726: 1 home in October 202678727: 1 home in October 202678729: 10 homes in October 202678730: 2 homes in October 202678731: 8 homes in October 202678735: 12 homes in October 202678736: 0 homes in October 202678739: 0 homes in October 202678741: 21 homes in October 202678742: 0 homes in October 202678744: 0 homes in October 202678745: 14 homes in October 202678746: 3 homes in October 202678747: 14 homes in October 202678748: 1 home in October 202678749: 1 home in October 202678750: 2 homes in October 202678751: 2 homes in October 202678752: 4 homes in October 202678753: 0 homes in October 202678754: 18 homes in October 202678756: 1 home in October 202678757: 9 homes in October 202678758: 0 homes in October 202678759: 0 homes in October 202612345
None1–45–910–1920+
ZIPHomesShare
1. 787042111%
2. 787412111%
3. 787541810%
4. 78747147%
5. 78745147%

Fastest riser: 78754, from 0 to 49 infill homes in Aug–Oct 2026 against a year earlier. Only permits inside the City of Austin full-purpose limits are counted, so ZIPs that straddle the city line show the city’s part only.

Who’s building

Milestone Community Builders, LLC led with 69 homes in the last six months.

BuilderHomesPermits
Milestone Community Builders, LLC6969
Trophy Signature Homes5454
Century Land Holdings II, LLC4848
New Home Co3333
Meritage Homes Corp2626

Infill homes permitted May – October 2026, out of 925. The permit holder is usually the general contractor rather than the developer, and one firm can appear under several names. 107 homes on 106 permits (12%) name no holder and are not ranked.