The Cedar Market Monitor is a monthly newsletter for the people building Austin's housing. We use public permit data to show where the market is heading: where new homes are going, how long approvals take, and who's building. This issue covers October 2026, with data
through 6 November 2026.
Last 3 months+47%424 permits Aug–Oct 2026, vs 288 a year earlier
Permit Issue time60 daysmedian SF, last 12 months
In the pipeline11,098permitted since Jan 2025, not yet finished
What got permitted
Detached houses carried 140 of October’s 188 infill homes.
Over twelve months infill homes are up 2%, and the missing middle was 19% of them, down from 24% the year before. Homes, not permits.
Pipeline
11,098 homes permitted since January 2025 haven’t been finished yet.
That’s the supply still coming: 85% of the
13,086 homes permitted in that time. 79% are in
apartment buildings (5+ homes), and five ZIPs hold
49% of them, led by 78702 (1,643) and 78758 (1,427). Most permits get built: 94% of homes permitted 2016–22 were finished.
Teardowns
Five ZIP codes had 64% of Austin’s 452 home teardowns in the last twelve months.
ZIP
Nov 2025 – Oct 2026
Year before
1. 78704
71
74
2. 78757
63
72
3. 78703
56
47
4. 78702
52
47
5. 78745
46
59
Private whole-house demolitions inside the City of Austin full-purpose limits, one per lot per year:
23 ZIPs in all (460 teardowns Nov 2024 – Oct 2025).
Permit issue time
A single-family permit takes a median 60 days to issue.
Building type
Permits
Median days
Excl. slowest 10%
Single-family
1,465
60
53
2–4 units
209
128
112
Multifamily & mixed use*
107
482
482
Median days from application to issue, permits issued Nov 2025 –
Oct 2026. The last column removes the slowest 10% to account for stalled
applications. *36% of multifamily & mixed use permits were applied for more than three years earlier, so that figure mostly reflects a backlog clearing.
Where
Five ZIP codes carried 47% of October’s infill homes.
None1–45–910–1920+
ZIP
Homes
Share
1. 78704
21
11%
2. 78741
21
11%
3. 78754
18
10%
4. 78747
14
7%
5. 78745
14
7%
Fastest riser: 78754, from 0 to 49 infill homes in Aug–Oct 2026 against a year earlier. Only permits inside the City of Austin full-purpose limits are counted, so ZIPs that straddle the city line
show the city’s part only.
Who’s building
Milestone Community Builders, LLC led with 69 homes in the last six months.
Builder
Homes
Permits
Milestone Community Builders, LLC
69
69
Trophy Signature Homes
54
54
Century Land Holdings II, LLC
48
48
New Home Co
33
33
Meritage Homes Corp
26
26
Infill homes permitted May – October 2026, out of
925. The permit holder is usually the general contractor rather than the
developer, and one firm can appear under several names. 107 homes on 106 permits (12%) name no holder and are not ranked.